Rumour list
Rumour List current as of June 19, 2024
The List is subject to change. It is for general information only and is based on input from various sources. The information posted is in no way final or guaranteed.
Wood Buffalo Region | Central Alberta | Southern Alberta
Wood Buffalo Region
Approx Start Date
Worksite
Approx Duration
Cntr
Type
Agrmt
Approx M/P
AUGUST 2024
Conoco Phillips
2 Week +
Altex Field Services
Exchangers
ABMA
32
AUGUST 2024
Suncor Firebag
1 Week +
CEDA
OTSG
ABMA
24
AUGUST 2024
Suncor Plant 52
1 Month +
APTIM
Turnaround
ABMA
178
AUGUST 2024
Suncor Plant 53
1 Month +
APTIM
Turnaround
ABMA
24
SEPTEMBER 2024
Syncrude
2 Weeks +
CIMS
Turnaround
ABMA
30
SEPTEMBER 2024
Albian Sands
1 Week
CIMS
Turnaround
ABMA
30
SEPTEMBER 2024
MacKay River
1 Month +
Melloy
Turnaround
ABMA
50
Approx Start Date | Worksite | Approx Duration | Cntr | Type | Agrmt | Approx M/P |
AUGUST 2024 | Conoco Phillips | 2 Week + | Altex Field Services | Exchangers | ABMA | 32 |
AUGUST 2024 | Suncor Firebag | 1 Week + | CEDA | OTSG | ABMA | 24 |
AUGUST 2024 | Suncor Plant 52 | 1 Month + | APTIM | Turnaround | ABMA | 178 |
AUGUST 2024 | Suncor Plant 53 | 1 Month + | APTIM | Turnaround | ABMA | 24 |
SEPTEMBER 2024 | Syncrude | 2 Weeks + | CIMS | Turnaround | ABMA | 30 |
SEPTEMBER 2024 | Albian Sands | 1 Week | CIMS | Turnaround | ABMA | 30 |
SEPTEMBER 2024 | MacKay River | 1 Month + | Melloy | Turnaround | ABMA | 50 |
Central
Approx Start Date | Worksite | Approx Duration | Cntr | Type | Agrmt | Approx M/P |
JUNE 2024 | Nutrien Redwater | 2 Weeks + | Melloy | Turnaround | ABMA | 20 |
AUGUST 2024 | Nutrien Redwater | 1 Month + | Melloy | Turnaround | ABMA | 60 |
SEPTEMBER 2024 | Shell Scotford | 3 Weeks + | Waiward | Turnaround | ABMA | 80 |
Southern
Approx Start Date | Worksite | Approx Duration | Cntr | Type | Agrmt | Approx M/P |
JUNE 2024 | Joffre Nova | 38 Days | Melloy | Exchangers, Towers, Drums, Vessels | ABMA | 80 |
JUNE 2024 | Joffre Nova | 3 Weeks + | CEDA | Turnaround | ABMA | 68 |
AUGUST 2024 | Joffree Nova | 40 Days | Melloy | Exchangers, Towers, Drums, Vessels | ABMA | 120 |
AUGUST 2024 | Joffre Nova | 1 Month + | CEDA | Turnaround | ABMA | 104 |
AUGUST 2024 | CF Medicine Hat | 4 Weeks | Clearwater | Turnaround- Offering Incentives (FM Rate for JM, 7 days LOA) | ABMA | 70 |
SEPTEMBER 2024 | Nutrien Carseland | 28 Days | Melloy | Shutdown | ABMA | 100-120 |