Boilermakers Lodge 146

Rumour list

Rumour List current as of June 19, 2024

The List is subject to change.  It is for general information only and is based on input from various sources.  The information posted is in no way final or guaranteed.

Wood Buffalo Region | Central Alberta | Southern Alberta

 

Wood Buffalo Region

Approx Start Date

Worksite

Approx Duration

Cntr

Type

Agrmt

Approx M/P

AUGUST 2024

Conoco Phillips

2 Week +

Altex Field Services

Exchangers

ABMA

32

AUGUST 2024

Suncor Firebag

1 Week +

CEDA

OTSG

ABMA

24

AUGUST 2024

Suncor Plant 52

1 Month +

APTIM

Turnaround

ABMA

178

AUGUST 2024

Suncor Plant 53

1 Month + 

APTIM

Turnaround

ABMA

24

SEPTEMBER 2024

Syncrude

2 Weeks +

CIMS

Turnaround

ABMA

30

SEPTEMBER 2024

Albian Sands

1 Week

CIMS

Turnaround

ABMA

30

SEPTEMBER 2024

MacKay River

1 Month + 

Melloy

Turnaround

ABMA

50

Central

Approx Start Date

Worksite

Approx Duration

Cntr

Type

Agrmt

Approx M/P

JUNE 2024

Nutrien Redwater

2 Weeks +

Melloy

Turnaround

ABMA

20

AUGUST 2024

Nutrien Redwater

1 Month +

Melloy

Turnaround

ABMA

60

SEPTEMBER 2024

Shell Scotford

3 Weeks + 

Waiward

Turnaround

ABMA

80

Southern

Approx Start Date

Worksite

Approx Duration

Cntr

Type

Agrmt

Approx M/P

JUNE 2024


Joffre Nova

38 Days

Melloy

Exchangers, Towers, Drums, Vessels

ABMA

80

JUNE 2024

Joffre Nova

3 Weeks +

CEDA

Turnaround

ABMA

68

AUGUST 2024

Joffree Nova

40 Days

Melloy

Exchangers, Towers, Drums, Vessels

ABMA

120

AUGUST 2024

Joffre Nova

1 Month +

CEDA

Turnaround

ABMA

104

AUGUST 2024

CF Medicine Hat

4 Weeks

Clearwater

Turnaround- Offering Incentives (FM Rate for JM, 7 days LOA)

ABMA 

70

SEPTEMBER 2024

Nutrien Carseland

28 Days

Melloy

Shutdown

ABMA

100-120